The time it takes to remodel a kitchen t(p) varies inversely with the number of workers assigned to the job p. A kitchen remodeling job takes 40 hours to complete when 2 workers are assigned to it. Which equation can be used to find the time to complete the job when p workers are assigned to it. A. t(p)=40pB. t(p)=8pC. t(p)=80/pD. t(p)=20/p